[ARCHIVED] Tentative Uptown Street Improvement Schedule

Mountain West Holding Company, the successful bidder to stripe Butte’s new bike routes and parking lines, as well as install new signage have presented the Butte-Silver Bow Public Works Department with a tentative timeline for work completion. Mountain West Holding Company will be providing notices to residents and business regarding their vehicles, parking lots, and driveways in the impacted areas. The tentative schedule is as follows:

Street Sign Base Installation:
Wednesday, September 9, 2015 – Mercury and Washington Streets
Thursday, September 10, 2015 – Granite Street
Friday, September 11, 2015 – Main Street

Sign Hanging:
Monday, September, 14, 2015 – Mercury and Washington Streets
Tuesday, September 15, 2015 – Granite Street
Wednesday, September 16, 2015 – Main Street

Street Striping:
Monday, September 14, 2015 – Mercury, South Dakota and Colorado Streets
Tuesday, September 15, 2015 – Broadway, Idaho and Wyoming Streets
Wednesday, September 16, 2015 – Granite and Washington Streets
Thursday, September 17, 2015 – Main Street
Friday, September 18, 2015 – Main and Galena Streets

For more information, please contact Keith Johnston at Mountain West Holding Company at (406) 497-1422, Andy Dare at Pioneer Technical at (406) 723-1949 or Butte-Silver Bow Roads Engineer Nick Sandford at (406) 497-6576.